Thursday, 21 December 2017
Rough Scarifying Work
Monday, 4 December 2017
Hollow coring work on approach areas.
Coring work was carried out on some of the softer approaches to remove some organic matter. Approaches at 2,6,8,9,10,16th will be done, with a heavy sand dressing afterwards worked into the holes.
Wednesday, 15 November 2017
Fraser's Kilimanjaro Climb
Well done Fraser.
Tuesday, 14 November 2017
Greens verti draining
The greens were verti drained with 12mm solid tines to a depth of 300mm. A slight heave was applied to the heads to shake up the profile. Rolling was done afterwards to return the surface to normal. There was no requirement to do the 5th green that was re laid last winter.
Friday, 10 November 2017
8th green Silverburn update.
Work has progressed well this week with irrigation and drainage work completed. Final raking on the root zone and we were ready for turf. The green and approach were done first then the surrounds. New turf was purchased for the surrounds and 9th tee. The project is almost complete after ten days. Great work from the contractors Greentech Scotland under the supervision of Colin Buchanan and his team. Fraser Jardine will now nurse it through the winter and get it ready for play in April.
Fairway Verti draining.
The 7th fairway is very wet due to the excessive rainfall over the past few weeks. This fairway sits on a seam of grey clay which slows down drainage from the turf surface. 30 ton of sand was applied before it was verti drained with 25mm tines to a depth of 400mm. This will help in the short term but long term it needs a complete new drainage system to catch surface water before it reaches the clay layer.
Tuesday, 31 October 2017
Green overseeing
During the maintenance week the greens were punch tined with 12mm tines to a depth of 25mm. Bar fescue seed was applied by hand and brushed into the holes. 20kgs of seed was applied to each green. A pass was made with the vredo overseeder planting more fescue and some Bent grass. Sand dressing was applied afterwards and worked into the holes filling them to the top.
Monday, 30 October 2017
8th Green Silverburn
Work begun today to re-build the 8th green on Silvetburn. This green was very poorly constructed in the 1970s when the course was extended to 18 holes. The root zone and subsoil will be removed and new drainage will be installed under and round the new green to ensure that the area is kept dry. These pictures show the state of the soil and subsoil below the green. Large stones.clay and silt layers all the way through the profile.
Tuesday, 19 September 2017
Rough Treatment
After mowing out the main rough areas we have now sprayed them with herbicide and gramicide to remove weeds and Yorkshire fog/Rye Grass. Once the chemicals have killed these weeds/ grasses raking will be done with the terra take to rip out thatch and dead grass
Wednesday, 2 August 2017
Foliar application to greens.
Tuesday, 20 June 2017
Rough Thinning Work
Friday, 2 June 2017
Seeding Time
Tuesday, 23 May 2017
Fairway Dressing
Sunday, 30 April 2017
Gorse Area 4th Hole Silverburn
Friday, 28 April 2017
Green Over seeding results
Thursday, 27 April 2017
Rough management update
Friday, 14 April 2017
5th green Update
Wednesday, 22 March 2017
Course Information
We have started to punch tine the greens to allow new seed to be dropped into the holes. The holes are 25mm deep, with new seed brushed in and dressed with sand to fill the hole. There will be no more over seeding on green during the playing season. This will be done again in October when the course is closed for 4 days.
Directional sleeper signs have been placed at certain holes to help speed up play for visitors and guests. Old sleepers were used to maintain the theme used in other areas round the course.